June 2002 - Installation and Commissioning of 1000 Amps thyristor unit for ELF NIGERIA Obite gas plant, Rivers state.
July 2003 - Commissioning of gas flowmeters at SHELL sea eagle vessel through HALLIBURTON near Warri, Delta state.
September 2003 - Installation and Commissioning of 16 cement silos level measurement using Endress level flex(radar on rope) and SCADA via profibus communication Flour Mills of Nigeria
November 2003 – Design, Supply, Install and Commission petroleum gas measuring system for River state Government gas consumers (FIRST ALUMINIUM, WEST AFRICAN GLASS INDUSTRIES, GENERAL AGRO OIL)
February 2005 – design, install and commission CO2 gas flow measuring and recording system for Guinness Nigeria, Aba Brewery.
June 2005 – design, supply, install and commission 14 motors/pumps and hydraulic control system for Unilever Nigeria, Oregun tooth paste plant.
November 2005 – design and supply motors multiple speed control panels for SONA BREWERIES (Champion Brewery, Uyo).
June/July 2006 - Carried out Installation and Commissioning of Batch automation system for Coca Cola Nigeria, Otta
December 2006 - Commissioned 20 pcs of radiometric level measurement for Dangote Cement, Obajana - Kogi state.
Febuary 2007 - Carry out servicing of complete instrumentation of beer packaging line for Guiness Nigeria lc, Aba Brewery.
July 2007 - Service and Calibrate capacitance level measuring system at BOURBON Hidra ship.
October - December 2007 - Design, Supply, Install and Commission natural gas metering system for First Aluminium, Easter Enamel, Air Liquide, Nigerian Engineering Works in Port Harcourt.
|
|
|
|